Cork Airport Business Park

0.7 km of single carriageway road, sewers, water mains, services, pump station & retaining walls


Client :
Value : € 2,000,000
Start Date :
2004
Completion Date :
2005


Consultants

Ray Kirby-Barry Kelliher & Associates



General Description

Cork Airport Business Park Phase 2 This project consisted of 0.7 km of Carriageway, with sewers, water mains, services and pump stations, attenuation tanks & Retaining walls



Features

  • 0.9km surface water pipes
  • 3no surface water holding tanks
  • 0.9km Foul Sewer
  • 160 m Retaining walls
  • 3no ESB substations
  • 0.7km Bituminuous surfacing roadway complete with Kerbs
  • Walls & Fencing